SPRINT 2
Sprint 2 Goal:
Our goal was to finish up inventory, pictures for inventory items, and label the quadrants that we are organizing the inventory in.

Tasks:
To Do List Sprint 2
-
Finish tagging and photoing of flats in pit-3/20 & 3/27
-
Finish flats by wall, rolly chairs
-
-
Finish tagging furniture on right/left loft-3/20 & 3/27
-
Left loft, Wednesday (27th)
-
-
Start tagging tools-3/20 & 3/27
-
Bruce will group tools and take pictures
-
-
Take pictures of Steps-3/20 & 3/27
-
Categorize props-3/25. (must be on mondays to meet with Carol)
-
Finish-must take pictures of quadrants and input data
-
-
Find duplicates and inaccurate data in inventory system (clean up): 3/18-4/1
-
Continuous process
-
-
Start implementing photos in system: 3/18-4/1
-
Developing check in/out: 3/18-4/1



Review:
We met with Bruce (and Tom Mellor made a surprise appearance) to show what we've accomplished. We opened up the excel sheet on the projector and showed all of the data that we've been able to insert and all of the photos we uploaded to the drive so far. We then explained our vision for Sprint 3 and asked if Bruce wanted us to make any late adjustments.
Retrospective:
This was the activity set up by Bill, our Scrum Master. It was "Sad,Glad,Mad." - Again, pretty similar to our retro in sprint 1 - But each team member contributed to what made them sad about sprint 2, glad about what happened in sprint 2, and what made them made about what happened in sprint 2. For example under Sad: "Not everyone was on time to work" or under Glad: "We made Bruce happy"....